Abstract: . . . feet [.91 meters] below ground. Closed-loop systems must be completely purged of heat transfer uid prior to 8 plugging. This uid must be disposed of in accordance with the provisions of North Dakota Century Code chapter 61-28 and other state laws and regulations. History: Effective March 1, 1984; amended effective October 1, 1990; December 1, 1992; January 1, 2008. General Authority: NDCC 38-19-03 Law Implemented: NDCC 38-19-03 . . . . . . may require a permit under North Dakota Century Code chapter 61-28 or North Dakota Administrative Code article 33-25. History: Effective March 1, 1984. General Authority: NDCC 38-19-03 Law Implemented: NDCC 38-19-03 43-02-07-15. Plugging and abandonment. Notice of intention to abandon any geothermal energy extraction facility must be led with the state geologist by the producer prior to the commencement of plugging operations, . . . . . . producer prior to the commencement of plugging operations, on a form prescribed by the state geologist. The notice must state the name and location of the well or well eld and the name of the producer. Before any geothermal energy extraction facility is abandoned, it must be plugged in a manner which will conne permanently all subsurface minerals, oil, gas, and water in the separate strata originally containing them. This operation . . . . . . prior to the commencement of plugging operations, on a form prescribed by the state geologist. The notice must state the name and location of the well or well eld and the name of the producer. Before any geothermal energy extraction facility is abandoned, it must be plugged in a manner which will conne permanently all subsurface minerals, oil, gas, and water in the separate strata originally containing them. This operation must . . . . . . pertinent information as may be requested by the state geologist. 2. 3. 4. History: Effective March 1, 1984; amended effective October 1, 1990. General Authority: NDCC 38-19-03 Law Implemented: NDCC 38-19-03 43-02-07-12. Production reports. The producer of each and every open-loop geothermal energy extraction facility shall on or before the rst day of February of each year le with the state geologist a sworn statement showing the . . . . . . by the commission. The commission shall advise the surety and the principal when liability on a surety bond is terminated. The state geologist is authorized to act for the commission as to all matters within this section. History: Effective March 1, 1984; amended effective October 1, 1990; December 1, 1992; April 1, 1994; May 1, 1994; May 1, 2004. General Authority: NDCC 38-19-03 Law Implemented: NDCC 38-19-03 43-02-07-09. Proof . . . . . . Renewal of Permit Bond Proof of Financial Responsibility Technical Requirements Completion Report and Basic Data Collected Production Reports Records to Be Kept Disposal of Unusable Products Plugging and Abandonment 43-02-07-01. Denitions. The terms used throughout this chapter have the same meaning as in North Dakota Century Code chapter 38-19, except: 1. "Closed-loop system" means any geothermal energy extraction facility, vertical, . . . --3000,7,214,3538,19080
|