|
Abstract: . . . – Approximately $21.5 million in land lease payments 14 High Winds Energy Center Project Schedule • Initially developed 1999-2000 • Delayed by – California energy crisis – PG&E bankruptcy – Enron collapse 15 High Winds Energy Center Project Permitting • 17 months – May 2001 – Sept. 2002 • EIR . . . . . . 2002 16 High Winds Energy Center Construction Schedule Phase I Roads Oct. – Dec. 2002 Foundations Jan. – Mar. 2003 Turbines Feb. – July 2003 17 High Winds Energy Center Construction Schedule Phase II Roads August 2003 Foundations September 2003 Turbines Nov. – Dec. 2003 18 . . . --586,2,146,711,2928
|